Securing a construction permit in Vietnam remains one of the most complex and challenging steps for foreign investors launching large-scale industrial projects. Given the continuous evolution of relevant decrees and construction laws, managing legal risk and ensuring timely project commencement is paramount.
As an experienced EPC contractor, Trung Hau Group offers a practical roadmap, not just a checklist. This guide demystifies the complex approval matrix, ensuring your FDI factory project achieves full compliance and commences on schedule.

1. Decoding the pre-construction approval roadmap
For Foreign Direct Investment (FDI) projects in Vietnam, the construction permit (CP) process is a sequential roadmap, not a simple application. The key to successful project management is shifting the focus from the CP submission date to the strategic completion of all prerequisites.

Why the construction permit is the final milestone, not the first step
The CP is the formal governmental certification that all essential investment, land, and technical requirements have been met. It is the end of the approval journey, not the start.
Investors must secure three prerequisites before the CP dossier is accepted:
- Investment Registration Certificate (IRC): Confirms the legal authority to execute the project.
- Legal Land Use Rights (LUR): Proof of secured land use rights, officially ratified by the Land Handover Minute.
- Basic Design Appraisals: Confirmation that the technical design complies with national building codes and safety standards (FPP and Environmental).
These components form the core of the building permit procedure in Vietnam, especially for industrial facilities and FDI manufacturing projects.
Key legal framework
The approval process is primarily governed by the Law on Construction 2014 (as amended) and the detailed procedural guidance found in Decree 15/2021/ND-CP. Understanding the practical application of these documents is crucial for minimizing back-and-forth with local authorities.
Project classification: how project grade determines the licensing authority
Project complexity is defined by its “Grade”, based on factors like size, capacity, and construction type. This grading directly assigns the competent authority responsible for issuing the construction permit in Vietnam:
- Grade I projects: Large, complex structures often require approval from the Ministry of Construction (MOC).
- Grade II and III projects: The majority of standard manufacturing factories and warehouses are handled by the Provincial People’s Committee (PPC) or the Industrial Zone Management Board (IZMB).
Identifying your project’s grade immediately clarifies the regulatory jurisdiction, enabling targeted risk and timeline management from day one.
2. The 4 core stages to completing the Vietnam construction permit process
Once the strategic prerequisites are understood, the application process can be broken down into four critical stages. Success relies on proactively managing the technical reviews (Stage 2) while formally completing the documentation required in Stage 1 and 3.

Stage 1: Establishing the legal and capacity foundation (pre-dossier) for your building permit in Vietnam
Before the construction permit (CP) application is even admissible, the investor must secure two main areas of foundation: legal right and technical capacity.
Investment Registration Certificate (IRC) and Legal Land Use Rights (LUR)
The legal foundation requires documented proof of your project’s legality:
- IRC: The Investment Registration Certificate confirming your legal authority to execute the project.
- Land Use: Valid Land Use Rights, typically demonstrated through a land lease agreement, but crucially, the Land Handover Minute from the competent authority confirming the cleared site is under your control.
The critical role of the design partner and EPC contractor
The CP dossier requires a Declaration of Capacity and Experience from the design contractor. This confirms their legal right and technical competence to design a project of your scale (Grade I, II, or III). Any gap in the designer’s licensing or relevant experience will result in dossier rejection, underscoring the necessity of vetting your technical partners early.
Stage 2: Mandatory design appraisals (the critical bottlenecks)
Stage 2 involves technical reviews by specialized agencies (Fire Police, Construction Agency, Environment Agency). These appraisals are the primary source of project delays and must be cleared before the final CP application.
Basic design appraisal (by the Specialized Construction Agency)
The Basic Design must be reviewed by the relevant Specialized Construction Agency (under the PPC or MOC). This appraisal verifies the design’s compliance with local architectural plans, structural integrity, and Vietnamese Technical Regulations (QCVN). The official assessment result is a mandatory document for the final CP submission.
Fire prevention and fighting (FPP) design approval
This is the non-negotiable step that causes the most frequent and longest delays. The Fire Police Department must issue approval for your FPP Design. This review assesses compliance with stringent standards, primarily QCVN 06:2022/BXD, covering fire safety systems, evacuation routes, and separation distances. Full integration of FPP requirements into the design from the start is essential to avoid lengthy re-submissions.
Environmental Permit (EP) integration
Under the Law on Environmental Protection 2020, most large manufacturing facilities must secure an Environmental Permit (EP). This document confirms the factory’s design—including waste treatment and emissions controls—meets national standards. The EP approval must be included in the CP dossier.
Stage 3: Construction permit application and competent authorities
This stage is the formal submission and review of the complete dossier, including all Stage 1 legal documents and all Stage 2 technical approvals.
Essential dossier checklist for industrial projects
The core documents required for the formal CP application include:
- Application Form
- IRC and ERC
- Legal Land Use Rights Document (including the Land Handover Minute)
- Design Appraisal Results (Basic Design and FPP Approval)
- Environmental Permit (EP)
- Design Contractor Capacity Declaration
The licensing authority: where to submit your application (PPC vs. MOC)
The responsible authority is determined by the project’s Grade and location:
- Industrial Zone Management Board (IZMB): Handles most standard factories within their managed zones.
- Provincial People’s Committee (PPC) / Department of Construction: Typically handles Grade II or off-zone Grade III projects.
- Ministry of Construction (MOC): Issues permits for highly complex Grade I projects.
Official processing timeline (30 days) vs. realistic expectations
The legal processing time for a valid and complete CP dossier is 30 working days.
Crucially, the 30-day clock only starts after the dossier is deemed complete and valid. Investors must plan for a realistic total pre-construction approval timeline of 4–6 months to account for the prerequisite Stage 2 approvals (FPP, Basic Design, and EP), which require rigorous preparation and negotiation.
Stage 4: Post-permit obligations (before and during commencement)
Once the CP is issued, final administrative steps must be taken before mobilizing the site:
- Notice of commencement: A written notice of the planned start date must be sent to the local People’s Committee and the permit-issuing authority at least three working days prior to commencing work.
- Site management and safety: Ensuring all required safety standards (Law on Occupational Safety and Health) and quality controls are established on site.
3. Risk mitigation strategies for the construction permit in Vietnam
The regulatory process is fixed, but its efficiency is not. A local, integrated EPC contractor brings essential practical expertise that shifts the focus from passively submitting documents to proactively managing regulatory risk and accelerating the schedule.

The 3 most common causes of permit delays
Based on our extensive experience handling complex industrial permits, three recurring issues consistently derail project timelines, often adding four to six months of unforeseen delay:
- Cause 1: Design non-compliance with FPP or Vietnamese building codes (TCVN/QCVN). The most frequent failure point is submitting a design that fails to fully comply with the stringent QCVN 06:2022/BXD (Fire Safety of Buildings) or other relevant TCVN (Vietnamese National Standards). Since the FPP appraisal is a prerequisite for the CP, failure here stops the entire process. This often stems from foreign design teams not adapting international standards to strict local requirements.
- Cause 2: Complexities in site clearance or incomplete land documentation. Even with a signed Land Lease Agreement, the absence of the official Land Handover Minute or unexpected issues regarding residual site clearance (e.g., utility relocation) can halt the CP submission. This risk is higher for greenfield sites and large plots.
- Cause 3: Poor coordination between multiple regulatory agencies. The permitting process requires sequential approvals from the Department of Planning and Investment (DPI), the Fire Police, the Department of Natural Resources and Environment (DoNRE), and the Department of Construction (DoC). Failure to manage the cross-agency information flow effectively often leads to communication gaps and unnecessary lag time.
The advantage of integrated Design-Build (D-B) and EPC models
For foreign investors seeking speed and single-point accountability, the integrated EPC or Design-Build model is often the optimal strategy for permit management.
The EPC contractor assumes full responsibility for design, permitting consultation, and construction. This allows the team to initiate Design Appraisals (Stage 2) concurrently with the Legal Foundation steps (Stage 1). Crucially, the in-house design and technical teams ensure FPP and environmental requirements are integrated into the design from the very first draft, eliminating the risk of rejection in later stages. This integrated approach is the most effective way to compress the overall project schedule.
Cases where industrial projects are exempt from permits
It is important to know when the CP is not required, as this can drastically speed up smaller projects or internal modifications. Exemptions generally apply to:
- Minor structures: Temporary works used only for the execution of the main construction project.
- Utility infrastructure: Internal technical infrastructure located within the boundaries of the approved main project (e.g., internal roads, drainage systems).
- Internal renovations: Alterations or repairs that do not change the structural load-bearing elements, change the building’s function, or affect the fire safety distance.
Always consult with your EPC partner to confirm whether an exemption applies, as misinterpretation can lead to significant fines.
Obtaining a construction permit in Vietnam is not just paperwork. It is a coordinated legal, technical and regulatory pathway involving multiple authorities. With an integrated EPC model, Trung Hau eliminates the typical bottlenecks (FPP, EP, basic design) by managing them in parallel — shortening the approval timeline by several months.
If your project requires a fast, compliant start, our EPC team can support end-to-end permitting, technical design integration and multi-agency coordination.
Contact us:
- Address: 96M Hoang Quoc Viet Street, Tan My Ward, Ho Chi Minh City
- Hotline: (+84) 28.3785.3765
- Website: www.trunghaugroup.com
- Email: info@trunghaugroup.com