In industrial construction, the construction contract is the strategic tool that determines how risk, cost, schedule, and responsibility are allocated. The correct contract choice is the first step for the Owner to control the budget and optimize project efficiency.

This article delves into the analysis of 5 key types of construction contracts, from the traditional Lump-Sum to the advanced Guaranteed Maximum Price. Trung Hau will clarify how each contract type impacts your project’s risk profile, providing Owners with a comprehensive view to make the most informed decision for their factory, warehouse, and technical infrastructure projects.

1. Construction contracts overview

1.1. The strategic importance of contracts

The selection of a construction contract type is not merely an administrative or legal formality; it is a profound strategic business decision. This choice fundamentally dictates how risk will be allocated, costs will be controlled, and the overall potential for project optimization will be realized. Especially within the industrial construction sector – where facility projects demand high technical precision and strict adherence to timelines – understanding the operational mechanics of each contract is paramount for the owner to secure their investment and maximize its value.

1.2. What is a construction contract?

A construction contract is the binding legal agreement between the owner and the contractor. Its role is to explicitly define the scope of work, cost, time frame, and respective responsibilities of all parties involved in the execution of the project. It serves as the legal framework guaranteeing that the project will be delivered in accordance with the established technical and commercial commitments.

1.3. Essential contract terminology

For an owner to effectively participate in contract negotiation and project management, familiarity with the following core terms is essential:

  • Scope of Work (SOW): The detailed and clear definition of all labor, materials, and services the Contractor must provide. The more precise the SOW, the lower the risk of future disputes.
  • Change Order (CO): A formal, approved document used to modify the original contract’s scope, cost, or schedule. Uncontrolled change orders are the primary cause of cost overruns and delays.
  • Value Engineering (VE): A systematic, function-oriented analysis process aimed at optimizing the design, reducing the initial investment or operational costs without compromising the quality, function, or performance of the facility.

2.  5 key types of construction contract that every owners need to know

In industrial construction, the following five contract types form the backbone of project execution. The owner’s choice of contract determines whether risks related to cost, schedule, and quality are transferred or retained.

2.1. Types of construction contracts: Lump-Sum Contract (Fixed-Price)

This is a traditional contract where the contractor agrees to complete the entire SOW for a single, fixed price. This contract is ideal when the design is over 90% complete, and consequently, the risk of cost fluctuations (materials, labor) is completely transferred to the contractor. To mitigate risks associated with the SOW, the owner should mandate a constructability review by a third party or internal engineering department before signing.

Pros:

  • The total investment cost is accurately determined upfront, providing the owner with maximum budget certainty.
  • Contract administration becomes simpler, reducing the complexity of day-to-day cost tracking and auditing.

Cons:

  • Low flexibility: Any changes (COs) require costly negotiation and are typically billed at premium rates.
  • Potential quality risk: The contractor might seek to cut costs if they face cost overrun risks, potentially affecting material quality or construction workmanship.

2.2. Types of construction contracts: Cost-Plus Contracts

The owner pays all actual costs incurred by the contractor, plus a fixed or percentage-based fee (profit). Under this model, the owner will bear the highest cost risk, as the entire responsibility for cost escalation rests with the owner. To limit this exposure, the owner should require the contractor to commit to an interim cap for initial design/procurement phases.

Pros:

  • Maximum flexibility: The owner can easily modify the design and materials during the construction process.
  • Quality focus: The contractor is not pressured to cut costs and can instead focus on the quality of construction and engineering.

Cons:

  • High risk of budget overrun: Overall budget control is difficult, making the project highly susceptible to cost overruns without strict control mechanisms.
  • High oversight demand: Requires the owner to maintain a rigorous auditing and supervision department to verify the reasonableness of every incurred cost.

2.3. Types of construction contracts: Guaranteed Maximum Price (GMP) Contracts

The contractor guarantees that the total cost will not exceed a pre-agreed maximum price. If the actual costs are lower than the cap, the savings are shared. This model creates a balanced risk allocation between the two parties, limiting the owner’s cost increase risk to the defined cap. To maximize the contractor’s incentive to save costs, the owner should negotiate a balanced Shared Savings split (e.g., 50/50 or 60/40) to maintain high motivation.

Pros:

  • Budget assurance: The owner is protected from the risk of exceeding the predetermined maximum price.
  • Incentive for savings: The Shared Savings mechanism encourages the contractor to seek value engineering (VE) solutions and cost efficiencies.
  • Schedule flexibility: Allows construction to start early while design optimization can continue.

Cons:

  • Administrative costs: Requires higher contract control and management costs due to the complexity of tracking actual costs against the cap.
  • Contractor risk: If the initial estimate falls below the actual project costs, the contractor may incur a loss of profit or project loss.

2.4. Types of construction contracts: Unit Price Contracts

Payment is based on an agreed-upon fixed unit rate multiplied by the actual quantity of work completed. This contract type is common for earthworks or piling. Accordingly, the risk of quantity increases belongs to the owner, while the unit price risk belongs to the contractor. To avoid payment disputes, the owner must clearly define the quantity measurement method in the contract (e.g., actual field measurement vs. delivery tickets).

Pros:

  • Transparent unit pricing: Easy to compare bids between contractors and transparent regarding the cost of individual work items.
  • Quantity flexibility: Suitable when the SOW quantities are uncertain, allowing for smoother project execution.
  • Shared risk: Unit price risk belongs to the contractor, and quantity risk belongs to the owner, creating a clear division of responsibilities.

Cons:

  • Total cost uncertainty: The final cost is only determined when all quantities are measured, creating budget uncertainty for the owner.
  • Lack of incentive: This contract does not incentivize the contractor to seek innovative solutions for cost savings or schedule reduction.

2.5. Types of construction contracts: Time and Materials (T&M) Contracts

Payment is based on the actual hours worked by labor and the actual cost of materials used. Because there is no cost limit, this contract carries a very high cost risk for the owner. It is typically reserved for work where the SOW is poorly defined. To manage the initial budget, the owner should establish a not-to-exceed cap for small repair or renovation tasks.

Pros:

  • Maximum flexibility: Ideal for work where the scope or duration cannot be accurately quantified (e.g., emergency repairs, minor renovations).
  • Reduced volatility risk: Mitigates the risk for the contractor in case of sharp fluctuations in material or labor costs.

Cons:

  • Lack of cost control: The greatest risk of budget overrun because the contractor has little incentive to complete the work quickly.
  • High audit demand: Requires the owner to rigorously audit labor time sheets and material purchase invoices, reducing transparency regarding the total cost.

3. Types of contracts in construction based on project delivery methods

The choice of contract type is always intertwined with the project delivery methods. This section will analyze this relationship in detail, as the project delivery model is a direct factor in determining risk allocation and which contract type should be prioritized.

3.1. Analysis by project delivery method

Project delivery models shape how the involved parties collaborate and bear responsibility. The selection of a model determines which contract type will be prioritized.

Design-Bid-Build (DBB) – The traditional model

A linear model where design, bidding, and construction are three distinct phases.

  • Preferred contract: Typically uses lump-sum contracts or unit price contracts, as the design is required to be fully complete before bidding.
  • Risk note: The DBB model demands that the owner ensures the design is absolutely complete; the risks associated with design errors and subsequent change orders (COs) will be very high if the initial design has flaws.

Design-Build (DB) – The integrated model

The Owner contracts with a single entity responsible for both Design and Construction.

  • Preferred contract: Often uses the GMP Contract.
  • Key benefit:
    • Reduces conflicts between the designer and constructor.
    • Creates an ideal setting for applying VE early in the design phase to optimize the total cost.

EPC/Turnkey (Engineering, Procurement, Construction) – The key-in-hand transfer

The contractor is fully responsible for the entire process (design, procurement of materials/equipment, and construction).

  • Preferred contract: Almost exclusively uses lump-sum contracts, but cost-reimbursable structures are becoming common for large, complex industrial projects due to market shifts.
  • Risk analysis:  The owner transfers a high level of risk—including cost, schedule, and performance risk—to the EPC contractor. However, the contractor typically does not bear risks related to unforeseen site conditions, regulatory changes, or owner-directed scope variations.

3.2. Other construction contract types

These contract types are typically used as supplementary clauses or within complex collaborative models.

Incentive construction contract

These are supplementary clauses embedded into fundamental contracts like lump-sum or GMP agreements. The main purpose of an incentive contract is to reward (bonus) the Contractor for meeting or exceeding targets (e.g., finishing the project ahead of schedule, achieving high quality metrics) and penalizing them for failure to meet those targets, thereby creating a maximum incentive for performance.

Integrated project delivery (IPD)

IPD is a highly advanced collaborative model where the owner, contractor, and design consultant sign a single, unified contract. The distinguishing feature of IPD is that the parties collectively share risks and rewards based on the project’s financial outcomes. This model is becoming a growing trend due to its ability to emphasize transparency, shared accountability, and encourage innovation throughout the entire project lifecycle.

4. Construction contract selection strategy

Contract selection is not merely a legal procedure but a strategic investment decision. To help the owner transform analytical knowledge into actionable decisions, we provide the core decision framework and practical principles. This is the key to accurately aligning project requirements with the optimal contract type, ensuring risk control and maximizing investment returns.

4.1. Key criteria for contract selection

This framework helps the Owner evaluate the project’s risks and priorities, leading to the selection of the most suitable contract.

Decision criteria Project condition Preferred contract
Design completion level Design is clear, over 90% complete, and validated. Lump-Sum, EPC
Design is unclear, requires flexibility and optimization. Cost-Plus, GMP
Cost risk tolerance The owner wants zero risk of budget overrun (Fixed Price). Lump-Sum, EPC
The owner is willing to share risk for speed (Fast-track). GMP, Cost-Plus
Optimization goal Priority is schedule or technical optimization (VE). GMP, Design-Build (DB)
Priority is the lowest initial bid (low bid). Lump-Sum, Unit Price

4.2. Cost optimization recommendations

Signing the contract is only the beginning; the owner must implement the following strategies to maximize cost efficiency:

  • Strategy 1: Establish price ceiling and savings incentives

Always upgrade cost-plus contracts by setting a maximum price (cap) to limit budget overrun risk. Simultaneously, utilize a shared savings mechanism to incentivize the Contractor to seek cost-saving solutions.

  • Strategy 2: Control change orders through early focus

Focus resources on the front-end engineering phase to ensure the design’s completeness and constructability. This is the key to minimizing change orders during construction, which are the main cause of overruns in fixed-price contracts.

The choice among 5 key types of construction contracts is ultimately a tool for strategic risk management. For industrial owners, models like GMP and EPC often provide the best balance, transferring cost volatility to the contractor while maintaining project efficiency and quality.