Amidst the wave of foreign direct investment (FDI) into Vietnam, the EPC contractor model has become the strategic choice for complex industrial projects. The core difference between an EPC contractor and a general contractor is the mechanism of cost and schedule risk transfer.
Drawing on the expertise of Trung Hau Group, this article provides an in-depth analysis of the EPC model, clarifies its distinction from the general contractor, and outlines optimal contractor selection criteria for the Vietnam market.

1. What is an EPC contractor?
An EPC contractor is a single entity responsible for the complete project lifecycle delivery. This responsibility spans from the initial engineering design phase through the procurement of all necessary equipment and materials, culminating in the construction and commissioning of the final operational facility. The model is characterized as “turnkey” because the owner receives a key to a completed, tested, and operational asset ready for commercial use.
Dissecting the three pillars of the EPC model
The success of the EPC model lies in the seamless integration of its three core functions, which inherently eliminates interface risks often present when managing separate design and construction contracts.
The success of the EPC model lies in the integration of its three core functions, which inherently eliminates interface conflicts and eliminates the owner’s risk exposure associated with managing separate design, procurement, and construction contracts.
- Engineering: This phase is critical as it determines the project’s performance and ultimate cost structure. The contractor is financially liable for any design errors, requiring rigorous control over processes ranging from conceptual design to front-end engineering design (FEED) for technical specification lock-down, and finally, detailed design for construction drawings. This emphasis ensures the design is inherently cost-optimized.
- Procurement: In procurement, the EPC contractor assumes full responsibility for the complex supply chain. This involves activities like global sourcing and local sourcing, rigorous vendor vetting, contract negotiation, and managing all logistics and customs clearances. Crucially, the EPC contractor absorbs the risk of material cost escalation, currency fluctuations, and any delays within the supply chain, ensuring cost and schedule predictability for the owner.
- Construction: This is the phase of integrated execution where the finalized design and procured materials are physically brought together on site. The contractor is fully accountable for strict adherence to quality control (QC/QA) and safety (HSSE) standards, managing all necessary subcontractors, and executing the critical pre-commissioning and testing phase before the final handover.

Lump Sum Turnkey – LSTK: the core of EPC
The LSTK contract is the fundamental legal expression of the EPC commitment.
- Defining LSTK: it represents the contractor’s firm commitment to deliver the entire defined scope of work for a fixed price and by a guaranteed completion date.
- Core benefit to the owner: this provides essential budget and schedule certainty. FDI investors can effectively lock down the total project cost, shielding their financial plan from market volatility and transferring full cost/schedule risk to the EPC entity.
2. Comparison: EPC contractor vs. General contractor
The fundamental difference between an EPC contractor and a general contractor lies in the degree of responsibility and the allocation of project risk. While both manage construction, their contractual roles and accountability to the owner are fundamentally different.

Comparison criteria #1: Scope of work and single point of responsibility
The EPC model offers a comprehensive, integrated service, whereas the GC model is traditionally segment-focused.
- EPC: the scope is comprehensive (A-Z). The EPC contractor is responsible for the entire project lifecycle, encompassing everything from design documentation to final commissioning. This results in a single point of accountability for the owner, simplifying communication and reducing administrative burden.
- GC: the scope is limited, primarily focused on the physical execution of construction and site management. The owner typically manages and coordinates the design team and the procurement process separately.
Comparison criteria #2: Risk transfer mechanism
Risk allocation is the most critical factor influencing the choice between the two models, particularly for large capital expenditures.
- EPC risk: under the LSTK contract, the EPC contractor absorbs significant project risks, including design risk (ensuring the design is constructible and functional), material cost escalation risk, and schedule delay risk. This maximum risk transfer shields the owner’s budget and schedule.
- GC risk: the owner retains liability for crucial project risks, such as design errors or omissions, failures in equipment procurement, and cost overruns stemming from these issues. The GC’s liability is typically limited to the quality of the physical construction work itself.
3. Analysis of the EPC contract
The EPC contract, typically structured as LSTK, is a legally robust document designed to transfer risk and ensure performance certainty for the owner. Understanding its core clauses is vital for project governance and protecting the investment.

Protective mechanisms for the owner in an EPC contract
Since the owner agrees to a fixed price, the contract must incorporate strong financial safeguards to enforce the contractor’s commitment to cost and schedule. These are mandatory to protect the owner’s financial plan.
- Performance guarantees are mandatory financial instruments, typically in the form of surety bonds or bank guarantees, provided by the contractor. They serve as security to the owner, ensuring the contractor completes the work according to the contract specifications. The percentage and purpose of these guarantees are negotiated and fixed upfront.
- Liquidated damages (LDs) represent a pre-agreed financial remedy for the owner in case of contractor default; they are a genuine pre-estimate of loss, not a penalty. Time LDs are fixed daily or weekly amounts the contractor must pay if the project fails to meet the guaranteed completion date. Performance LDs are crucial for process or power plants, as these compensate the owner if the completed facility fails to achieve agreed-upon operational metrics (e.g., capacity, efficiency, consumption rates).
Managing scope changes in the LSTK model
In an LSTK environment, scope creep is a major threat to the fixed-price guarantee, thus change management must be highly rigorous and transparent.
- The contract mandates a strict procedure for variation orders (VOs) or change orders. The process requires that any proposed change, whether requested by the owner or initiated by the contractor due to unforeseen circumstances, must be meticulously documented and approved by the owner in writing before any work commences.
- The golden rule: the EPC contractor must not perform any additional work outside the scope without clear written confirmation and agreement on the resulting impact on the final price and guaranteed completion date. This prevents unilateral cost increases.
The role of the owner’s engineer
Even with the maximum risk transfer provided by an LSTK contract, the owner requires dedicated oversight to verify compliance and protect their interests.
The owner’s engineer is an independent consultant hired by the owner to act as their technical representative. Their role is to conduct monitoring and verification activities—such as reviewing detailed engineering designs, inspecting quality during construction, and certifying project milestones for payment. Crucially, the owner’s engineer must perform their duties without interfering with the contractor’s means and methods of execution, thus preserving the single point of responsibility of the EPC contractor.
4. Criteria for selecting an EPC contractor in vietnam
For foreign investors injecting capital into Vietnam’s industrial sector, the selection criteria must go beyond typical technical capability, focusing heavily on local regulatory adaptability and proven risk management in an emerging market context.

Demonstrated legal and technical capability (Proof of Capability)
Selecting an EPC authority requires concrete proof of performance, not just corporate size.
- The mandatory requirement is clear evidence of successfully delivering similar LSTK projects in Vietnam, verifiable by local operating assets (e.g., cold storage, high-tech manufacturing, data centers). This demonstrates the contractor’s ability to execute under the fixed-price, fixed-time constraint within the region.
- Financial transparency and the ability to furnish adequate professional liability insurance capacity are necessary to ensure that the contractor is robust enough to cover the transferred legal and financial risks of the project.
Deep understanding of Vietnam’s construction regulations (Local Regulatory Expertise)
This is the largest competitive differentiator and often the key factor determining the project’s success or failure in Vietnam. A professional EPC contractor must act as a legal navigator for the FDI owner.
- Specific knowledge of fire fighting approval: experience in obtaining fire prevention and fighting design appraisals and final acceptance in accordance with decree 136/2020/ND-CP and the latest technical standards is critically important to prevent project delays, which are a common barrier.
- Environmental impact assessment (EIA) and permits: the contractor must be able to integrate environmental requirements into the design phase, ensuring early compliance with local laws regarding EIA and environmental licensing.
- Construction permit procedures: fluency in current decrees and circulars (e.g., decree 15/2021/ND-CP on construction investment project management) drastically reduces time spent on licensing and approvals, often the most volatile element of a project schedule.
Comprehensive risk management processes
The contractor’s internal processes for managing construction risks must be rigorous.
- HSSE and quality track record: the contractor must demonstrate an internationally recognized quality management system and a strong safety record, ideally showing a zero lost-time injury rate.
- Controlling risks related to the workforce (manpower risk), site security, and local labor practices is vital for large-scale, long-term projects in the industrial zones of Vietnam.
The EPC contractor model stands as the superior strategic choice for complex, large-scale industrial investments. It is a comprehensive risk mitigation strategy, delivering the vital certainty required for modern capital expenditure through the single point of accountability. This empowers foreign investors to focus on core business while delegating full execution and regulatory risk to a specialized partner.
Are you considering the deployment strategy for your manufacturing facility or industrial base in Vietnam?
Contact Trung Hau Construction Group – a proven EPC contractor with local regulatory and technical expertise in Vietnam – to access specialized LSTK consultation and strategic FDI legal guidance.
- Address: 96M Hoang Quoc Viet Street, Tan My Ward, Ho Chi Minh City
- Hotline: (+84) 28.3785.3765
- Website: www.trunghaugroup.com
- Email: info@trunghaugroup.com